By the time the system was completed, our team had achieved great things and an impressive amount of material had been used:
Total floor space: 8,000 m²
Installed steel structure: 950 tons
Facade / trapezoidal sheet metal installed: 8,000 m²
Assembly hours (steel and equipment): 57,000 h
Truck-mounted cranes used: in addition to the 2 pcs. Bernegger mobile cranes in the 90 and 100 ton class, the complete crane product range from Felbermayr in the 70 - 500 ton classes was also used, which was finally rounded off by the use of a crane in the 650 ton class for several weeks for the furnace and boiler lifting - heaviest part to be moved: 85 tons with dimensions of approx. 4.5 x 4.5 x 26 m.
Pipelines installed: 145 tons / 9,000 running meters
Scaffolding installed: 2,800 m²
Installed cable routes: approx. 2,000 running meters
Installed cable lengths: approx. 55,000 running meters
9,600 m³ of concrete and 900 tons of reinforcing steel
The stair tower and elevator shaft (50 m high) were constructed using the slipform method within 12 days